Change management at an airline catering business using lean thinking

Change management at an airline catering business using lean thinking

Frank van Velzen
June 12, 2014

INTERVIEW - Having to adapt to changing customer needs, KLM Catering Services decided to turn to lean thinking, reducing its changeover times and recycling more.


Interviewee: Frank Van Velzen, Manager of Process Development, KLM Catering Services


Planet Lean: KLM Catering Services has been using lean for over eight years now - what challenges were you encountering when you decided to first adopt it?

Frank van Velzen: A visit from an airline caterer from the United States revealed the high levels of inventory we were carrying and all the overproduction we had. We were introduced to the methodology, studied it and realized it would match what we wanted the organization to look like in the future. We set off to start using the tools and techniques. Eight years down the line, we are moving towards a new organizational culture.

The biggest improvements we make result from our desire to meet customer demand, which is necessary for us to stay competitive as an airline.

PL: What has changed in the airline catering business in recent years?

FVV: Like many other industries, we have seen customers become increasingly demanding and expect service to be faster and more reliable.

Stocking up carts for up to 60,000 meals per day is a big task, and on top of that there are add-on services we must consider: for example, today passengers are allowed to purchase a meal upgrade at check-in. Upon assembling the cart, we need to take special meals into account, and place them in the right position in the cart depending on where the passenger who requested that meal is sitting.

For years, the choice the airline offered was limited (does “chicken or pasta” sound familiar to you?), and we could assemble carts half a day – sometimes even a day – before a flight. Now that our customers can upgrade their meal on their way to Schiphol or at check-in, things need to happen much more quickly. As an organization we had to become more flexible and dynamic in order to accommodate variation and meet shorter lead-times.

PL: How did you achieve that?

FVV: We did it in two ways, mainly. First of all, we set up a system of cells next to our production line; we are now working to stabilize all our processes, working to takt time and making the facility a safe place to work. Secondly, we are learning to analyze our data more effectively.

PL: Can I have an example of this?

FVV: Here’s one. We used to have 40 bottles of wine on our morning flights to Madrid, even though at that time of the day people only want coffee. We were flying liters and liters of wine all over the place for no reason. In the afternoon flight, we’d do the same mistake, but with coffee (everybody wanted to drink some wine after lunch).

We had to find a way to ensure people would have a choice while learning to look at our data in a different way, to understand what beverages work and what don’t on what flights. Why would I carry 10 cans of Schweppes if I know I am not going to need them?

PL: What is the most difficult part of managing change?

FVV: Definitely teaching the lean way to leadership, and how to be a coach and a mentor. Getting leaders to move away from the command and control mentality is extremely hard.

PL: Have you come across other airline caterers applying lean principles?

FVV: We have, but only a few. Many of them tell us that what we are trying to do has the potential to set new standards for the industry.

PL: Can you share some improvement figures?

FVV: Of course. We have been able to shorten our lead-time for the KLM Europe flight assembly from eight hours to maximum 10 minutes, for example, as well as reduce the turnaround time for Embraer planes from 50 to 35 minutes (which means one extra aircraft on the flight schedule). Recycling has gone up from 5 to 17% already, and the figure is growing. The KLM Intercontinental assembly line has seen changeover time reduced from 4 hours to 20 minutes a day (with a very large variety of products as well). In general the level of stock has dropped for almost all planes.


THE INTERVIEWEE

Frank van Velzen, Manager of Process Development, KLM Catering Services

Read more

Jishuken at a Coloplast distribution center
September 10, 2020
Jishuken at a Coloplast distribution center

VIDEO - In February, a group of Lean Global Network coaches visited Coloplast's Parts Distribution Center in Hungary to help the local team improve the internal lead-time across the facility.

Continue reading
Monozukuri, Hitozukuri, Kotozukuri
January 8, 2019
Monozukuri, Hitozukuri, Kotozukuri

RESEARCH – The authors present a new perspective on value creation. In addition to monozukuri (making things) and hitozukuri (making people), they discuss the idea of kotozukuri, making things happen.

Continue reading
Moving forward
September 5, 2019
Moving forward

INTERVIEW – This moving company in Singapore has taken its first steps down the lean road, reminding us that translating your strategy into small, actionable improvements people can make at the gemba is the way to a transformation.

Continue reading
The power of our origin story
October 23, 2018
The power of our origin story

PROFILE – Earlier this month, our editor visited the US and sat down with the CEO of a community health center near Boston. His humility and honesty about his lean leadership are striking.

Continue reading

Read more

No items found.